3.1.1 | Organization of a workshop in EU for SQF development with involvement of all project partners |
2
X
|
|||
3.1.2 | Development of the methodological basis & national model for SQFs by ANQF work group |
17
X
|
|||
3.2.1 | Procurement of necessary equipment for institutions involved in 5 SQFs development |
5
O
|
|||
3.3.1 | Setting up of 5 work teams to develop SQFs in the selected subject areas |
5
X
|
|||
3.3.2 | Organisation of focus groups for each subject area involving the work teams & stakeholders |
5
X
|
|||
3.3.3 | Development of the SQFs in the selected subject areas compatible with ANQF |
22
X
|
|||
3.3.4 | Piloting developed SQFs by referencing selected programmes to the SQFs |
35